Qingdao Zhongbo Steel Structure Co., Ltd. has a steel structure professional contracting engineering grade 3 qualification (brother company has steel structure A design qualification and professional contracting grade 1 qualification, curtain wall grade 1 qualification, external wall insulation grade 2 qualification), building decoration grade 2 qualification and anti-corrosion waterproof insulation grade 2 qualification, mainly to undertake Qingdao and Shandong steel structure house and plant construction projects. Steel structure plant transformation project, steel structure plant reinforcement, transformation, add layer and add construction to find Qingdao Zhongbo Steel Structure Co., LTD. Professional design, exquisite production technology, safe and fast installation and follow-up procedures of the professional, integrity of the credibility of cooperation, created Zhongbo steel structure from the design, factory processing, project contracting one-stop service of professional quality.
Please enjoy Qingdao Zhongbo Steel Structure Co., Ltd. project case show the old plant reinforcement and additional layer construction project
Project name: Old factory building renovation project of an enterprise in Zaohu Industrial Park
Project content: The old factory building was dismantled, the steel column was raised after the two-storey platform was added, and the roof was re-installed, so that the first-storey factory building became a high-end two-storey factory building, which improved the use area, strengthened the structural stability of the factory building, increased the corrosion resistance and extended the service life.
Commencement and completion date: December 2016 to March 2017.
After the steel structure plant is dismantled, add the middle column and add the layer
The protective demolition of the original plant makes the loss of the original structure small, the roof steel beam is retained, the reuse rate is retained to a greater extent, and the cost of the owner and customer is reduced.
After raising the steel structure column, the second floor platform on the beam.
Remove the gutter of the old factory building and replace it with 304 stainless steel gutter that is anti-corrosion and maintenance free for life. The roof beam of the second floor begins anti-corrosion treatment and installation.
Beginning to take shape, add layer reinforcement, please find Zhongbo steel structure:www.zhongboss.com
Began to install the roof purlin, roof galvanized purlin, Qingdao Zhongbo Steel Structure Co., Ltd. all their own workshop production, the more direct supply way, lower prices, to provide more composite national standards, quality and quantity of purlin and roof color steel plate.
The second floor began to lay floor bearing plate, 720 galvanized floor bearing plate, 688 galvanized floor bearing plate, Zhongbo steel structure can be processed, if you out of the material, we can provide pure processing services, the price of a province and then province.
The protective demolition of the original plant makes the loss of the original structure small, the roof steel beam is retained, the reuse rate is retained to a greater extent, and the cost of the owner and customer is reduced.
After raising the steel structure column, the second floor platform on the beam.
Qingdao steel structure plant transformation, reinforcement anti-corrosion, roof plate replacement, color steel plate anti-corrosion, please find Qingdao Zhongbo Steel Structure Co., LTD.
No. 178 Shuangyuan Road, Chengyang District, Qingdao
Jimo District Lancun Street office Nanquan Daijiazhuang No. 162-12 Zhongbo ecological Park
Laixi City 204 national highway around the ridge No. 2 Changjia Road, Industrial Park
13210005888